How to install pharmaceutical water purification equipment
Installing pharmaceutical water purification equipment involves a structured process to ensure regulatory compliance, system integrity, and product water quality. Below is a professional step-by-step guide tailored for pharmaceutical-grade systems like Purified Water (PW), Water for Injection (WFI), or Pure Steam Generators:
✅ Installation Steps for Pharmaceutical Water Purification Equipment
1. Site Preparation
Confirm URS (User Requirement Specification) and approved layout drawings.
Ensure availability of:
Clean room or classified area (if required).
Proper floor drainage and load-bearing structure.
Power supply, water inlet/outlet piping, and space for maintenance.
2. Unpacking & Inspection
Check equipment and accessories against packing list.
Inspect for transit damage.
Record serial numbers and equipment labels for validation.
3. Mechanical Installation
Anchor the system: Secure frame and base to the floor.
Connect piping:
Feed water inlet
Product water outlet
Reject water line
CIP/SIP lines if required
Use sanitary-grade piping (e.g., 316L stainless steel, orbital welded).
Maintain 3D dead-leg rules and slope for drainability.
Install pressure gauges, flow meters, and sampling points.
4. Electrical Installation
Connect to main power supply through a control panel.
Ensure earthing/grounding is in place.
Wire all instrumentation, sensors (TOC, conductivity, level), and control systems.
Configure PLC/HMI if automated.
5. Utility Connections
Connect:
Compressed air (for valves, if pneumatic)
Steam (for pure steam generator or SIP)
Cooling water (for multi-effect distiller)
6. Initial Cleaning & Sanitization
Flush the system with clean water to remove debris.
Perform chemical cleaning or passivation for stainless steel surfaces.
Sanitization using hot water, steam, or chemical agents (e.g., NaOH, H₂O₂).
7. Commissioning
Perform dry run to check pumps, valves, sensors, alarms, and control logic.
Operate with water to ensure:
Flow rates and pressure are as per design.
No leaks, vibration, or abnormal noise.
Verify instrument calibration.
8. Validation Support
IQ (Installation Qualification): Document installation conformity.
OQ (Operational Qualification): Test operating conditions.
PQ (Performance Qualification): Validate water quality and system performance.
9. Training & Handover
Train the client team on:
Start-up and shutdown procedures
Routine maintenance
Alarm handling
Provide as-built drawings, manuals, certificates, and validation documents.